Site Acceptance Tests (SAT) for transformers are crucial to ensure that the transformer has been installed correctly, functions according to the manufacturer's specifications and the client's requirements, and is ready for safe and efficient operation within its intended environment. Fistly we should do pre-test preparations of below:
Documentation Review: Verify that all necessary documentation is available, including installation manuals, factory test reports, wiring diagrams, and site-specific installation drawings.
Visual Inspection: Check for any physical damage during transportation and installation, proper alignment and securing of the transformer, and cleanliness of the installation area.
Safety Precautions: Ensure all safety measures are in place, such as grounding, fire protection systems, and personal protective equipment (PPE) for personnel.