SAT Electrical & Functional Tests

Released: 19/2/2023 18:10:06   Visits:1820

Transformer site acceptance tests including electrical tests and functional tests.

Electrical Tests

  1. Insulation Resistance Test: Measure the insulation resistance between windings and between windings to ground to verify integrity.

  2. Dielectric Strength Test (Hi-Pot Test): Apply a high voltage to check the transformer's ability to withstand electrical stress without breakdown.

  3. Winding Resistance Test: Measure the resistance of each winding to detect any abnormalities.

  4. No-Load Test: Perform with the transformer energized but without load to measure no-load losses and excitation current, indicating core condition and efficiency.

  5. Load Test: Apply a specified load to the transformer and measure voltage drops, currents, and losses to confirm performance under actual operating conditions.

  6. Temperature Rise Test: Monitor the temperature rise of the transformer under rated load to ensure it stays within allowable limits.

Functional Tests

  1. Control and Protection System Verification: Test all control and protection functions, including Buchholz relay, oil level indicators, temperature sensors, and cooling systems.

  2. Auxiliary Systems Check: Inspect and test auxiliary systems like fans, pumps, and heating systems for correct operation.

  3. Interlocking and Safety Features: Verify that all interlocks and safety mechanisms function correctly, preventing unauthorized access or operation under unsafe conditions.